East Link Extension
Connecting the Eastside with reliable light rail

News and updates

Project update

Upcoming I-90 ramp closures

Work continues to complete concrete work at the Mercer Island Station. Crews will continue pouring track slabs and sidewalks within the sound walls at the station platform. To safely do so, the…

Photo of Mercer Island station

Project update

Mercer Island Station Construction Nearing Completion

As we head into the fall, work at the Mercer Island Station is ramping up as crews work to put the finishing touches on the station. In the last few months, crews have: Completed installing the…

Project update

Island Crest Way Ramp Closures: Sept. 20 & 21 and 27 & 28

Track installation continues at the Mercer Island Station as crews prepare to pour the final track slabs at the Mercer Island Station platform.   To pour these slabs, crews will need to close…

Project update

Weekend Island Crest Way Ramp Closure: Sept. 14

Track installation continues at the Mercer Island Station as crews prepare to pour the final track slabs at the Mercer Island Station platform.   To pour these slabs, crews will need to close…

Project update

I-405 weeknight closures in downtown Bellevue on Wednesday, September 11th

Overnight drivers should be aware of upcoming lane and ramp closures on I-405 in downtown Bellevue. In preparation for East Link light rail, Sound Transit’s contractor crews will continue to paint…

Project update

I-405 weeknight closures in downtown Bellevue on Monday, September 9th

Overnight drivers should be aware of upcoming lane and ramp closures on I-405 in downtown Bellevue. In preparation for East Link light rail, Sound Transit’s contractor crews will be painting in…

Work will begin to build a temporary center platform at Pioneer Square Station later this fall.

Project update

Preparing Pioneer Square Station for Connect 2020

Preparation to connect light rail to the Eastside requires weekend shuttle buses between SODO and Capitol Hill on Oct. 12-13, Oct. 26-27, and Nov. 9-10 During three weekends this fall, Link light…

News release

Construction will close light rail in downtown Seattle on three weekends this fall

During three weekends this fall, Link light rail will not run between SODO and Capitol Hill while construction crews build a temporary center platform at Pioneer Square Station as Sound Transit…

Project update

Upcoming construction traffic impacts

I-405 to westbound I-90 overnight ramp closures and lane reductions on westbound I-90 Work continues on the cast-in-place long span rail bridge over I-90. Crews plan to close all ramps from I-405 to…

Project update

Weekend Island Crest Way Ramp Closures: August 17 & 24

Station construction has progressed this summer as crews have recently completed installing the steel for the platform’s canopy. In the coming weeks, work will continue to form and pour the concrete…