2. Timelines and milestones

  • Voter approval (2008)

  • Milestone Target
    Board identifies preferred package of improvements
    Issue State Environmental Policy Act Checklist for public review
    Board selects project to be built
  • Milestone Target
    Acquire property and obtain permits 2017 - 2021
    Complete parking garage design 2017 - 2021
    Groundbreaking 2017 - 2021
    Complete garage and surface lot construction 2017 - 2021
  • Start of service (2022)