Hilltop Tacoma Link Extension project phases

Image of Tacoma Link Extension timeline

Planning

Image of checkmark Evaluation (Summer 2013 – Spring 2014) COMPLETE

  • Identify route alignments within selected corridor for extension
  • Study route alignments and conduct early conceptual design
  • Host two open houses to gather public comments on alignments
  • Sound Transit Board identifies preferred alignment for extension

Image of checkmark Environmental Review and Conceptual Design (2014 – 2015) COMPLETE

  • Conduct conceptual design for selected alignment
  • Identify and gather public comments regarding station locations and site options for maintenance facility expansion
  • Determine type of environmental review documentation needed
  • Conduct environmental review and share results with public and agencies
  • Submit application for FTA New Starts/Small Starts grant funding
  • Conduct community and agency engagement

Design

Image of checkmark Final Design (Fall 2016 – Fall 2017) COMPLETE

  • Public open house and online survey to solicit feedback on 60% track and platform design and station naming
  • Finalize station and track design
  • Select local artist, Kenji Hamai Stoll, to design station art
  • Select permanent station names

Image of star indicating current phase Pre-construction (Fall 2017 – Summer 2018) CURRENT PHASE

  • Online and in-person open house in November 2017 to celebrate Final Design and kick-off pre-construction
  • Advance station art design
  • Define construction schedule and methods
  • Continue to partner with City of Tacoma and Pierce Transit
  • Obtain project building permits
  • Coordinate with private utility providers
  • Project update open houses
  • Outreach to local businesses and residents
  • Award light rail vehicle contract and construction contractor

Construction

Image of dotted circle indicating future project phaseConstruction and Testing (Fall 2018 – 2022)

  • Expected to begin as early as fall 2018 and be completed in 2022