12th Ave NE lane closure and early morning concrete pour at Roosevelt Station

What On Wednesday, July 24th, Sound Transit's contractor will be pouring the concrete steps at the north head house. Work will require a left lane closure on 12th Ave NE in order to bring in trucks…

Early morning crane work and sound wall removal at Roosevelt Station

What On Wednesday, July 10, Sound Transit's contractor will be using the mobile crane to load materials down the station's platform. Monday through Friday, July 8-12, Sound Transit's contractor…

12th Ave NE lane closure and early morning concrete pour at Roosevelt Station

What As early as Thursday, June 27th, to Tuesday, July 2nd, Sound Transit's contractor will be dismantling and removing the temporary construction elevator (IE "man lift") then pouring concrete to…

Sidewalk closure and no parking on portion of NE 67th St

What Starting as early as Monday, June 24th, Sound Transit's contractor will be performing utility work along the south sidewalk on NE 67th St between Roosevelt Way NE and 8th Ave NE. The north…

Update: Temporary Pedestrian and Bicycle Path on NE 65th Street and 12th Ave NE

What Sound Transit (ST) has an ongoing sidewalk closure on NE 65th St near 12th Ave NE in order to connect the Roosevelt Light Rail Station to underground utilities, install exterior wall panels,…

The craned nicknamed "Big Red" is dismantled at Roosevelt Station in March, 2019.

"Big Red" crane retirement marks another major step for trains to Northgate

Sound Transit recently said a fond farewell to the 280-foot-long tower crane, dubbed Big Red, after eight years of heavy-duty service hauling materials for two light rail station construction sites…

Roosevelt Station Crane Dismantling Watch Party, March 11 & 12

Sound Transit’s contractor will begin removal of the red Roosevelt tower crane starting as early as Monday, March 11. This is no small feat; the crane’s jib (the horizontal piece) alone is about 280…

Night-time noise: Utility work along 12th Ave NE

What On Sunday evening, March 10, Seattle Public Utilities will be connecting Roosevelt Station’s water line to the main water supply on 12th Ave NE near NE 66th St. When Sunday, March 10 from 5 p…

Tower Crane Removal at Roosevelt Station, March 11 - 15

What Starting, Monday, March 11, Sound Transit’s contractor will be dismantling the tower crane at Roosevelt Station. Work will be done in phases and will include evening work (see below). The work…

No parking along NE 67th St between Roosevelt Way NE and 12th Ave NE

What As early as Thursday, March 7, Seattle City Light will connect permanent power to Roosevelt Station on NE 67th Street along the north side of the Roosevelt Station site. No parking signs will be…