-
Voter approval (2008)
-
Milestone Target
Final Supplemental Environmental Impact Statement completed -
Design (2012-2014)
-
Milestone Target UW to Northgate tunneling excavation complete
2016 Northgate guideway construction complete
Track slab installation complete2018 Rail installation complete 2019 New light rail vehicles acquired 2019 Early system testing 2019 Elevators, escalators, and stairway construction to all stations complete 2019 Public artworks installed 2019 Roosevelt Station Complete 2019 U District Station Complete 2020 Northgate Station Complete 2020 System testing complete 2021 Open for service 2021 -
Open for service (2021)
Northgate Link Extension
Ride underground from downtown to Northgate